The Transmission Company of Nigeria (TCN), says that there will be power outage in its Amukpe substation for two weeks.
This is contained in a statement signed by the General Manager, Public Affairs TCN, Ndidi Mbah on Saturday.
Mbah said the disruption would begin on May 4 and would last till May 17.
According to TCN, the outage is to enable contractors have safe environment to erect two 132KV transmission towers at the substation.
TCN also said that as a result of the intending power outage, there would be no bulk power supply to Benin DisCo through the Adeje industrial, woodland, Mosogar, Sapele and Abraka feeders for the period.
“The transmission Company of Nigeria (TCN) hereby states that it will commence the erection of two (2) number 132kV transmission towers at its Amukpe Transmission Substation.
” And will equally restring a portion of the Benin-Delta and Delta-Oghara 132kV double circuit transmission lines from Saturday, May 4 to May 17, 2024.
“Consequently, Amukpe Substation will be out of power for the duration of the work.
“Also, there will be no bulk power supply to Benin DisCo through the following feeders: the Adeje, industrial Woodland, Mosogar, Sapele and Abraka feeders.
“The outage is necessary to create a safe working environment for the contractor. Completion of the projects will put in place N-1 redundancy that would enable TCN supply bulk electricity to the substation from either the Benin or Ughelli transmission line.
“This means that when one transmission line is faulty, bulk electricity can still be received in the substation from the second line., ” Mbah said.
TCN apologises for the inconvenience the development would cause to electricity consumers in the substation within the period.
She added that the projects would help ensure a more flexible and consistent bulk power supply through the Amukpe transmission substation when completed