- Two Mini-Grids Target Longstanding Electricity Gaps in Kano
The Rural Electrification Agency (REA) has commissioned two mini-grid projects in Kano State, targeting electricity access for 2,222 households in communities that have reportedly spent more than 16 years without power.
The projects comprise a 195-kilowatt-peak (kWp) mini-grid in Ballagaza and a 70kWp system in Marayar Rogo, Warawa, as the Federal Government expands efforts to extend electricity access through decentralised power infrastructure and private-sector investment.
Speaking at the commissioning ceremony, REA Managing Director Abba Aliyu said the projects contribute to the Renewed Hope Agenda’s target of providing electricity to more than 17 million Nigerians.
He described the installations as an example of how public-private partnerships can support rural electrification, while commending Kano State Governor Abba Kabir Yusuf for prioritising electricity access and creating an enabling environment for project implementation.

DARES Programme Supports Private-Sector Investment
Aliyu said Alfuttaim Nigeria Limited financed and constructed the mini-grids and would own and operate them over the long term, with government subsidies helping to make electricity more affordable for beneficiaries.
“The Federal Government did not build these mini-grids and hand them over. Alfuttaim Nigeria Limited invested its own money, built them, and will own and operate them for many years,” Aliyu said.
He explained that the Federal Government, through the Distributed Access through Renewable Energy Scale-up (DARES) programme, implemented by REA with support from the World Bank, subsidised part of the project costs.
According to Aliyu, Nigeria is targeting 1,350 mini-grids under DARES, while the programme has already delivered new or improved electricity access to more than five million Nigerians.
He said expanding access would require continued collaboration among government, private investors and beneficiary communities.
The REA chief argued that decentralised projects could help address Nigeria’s electricity deficit by extending supply to underserved locations, while encouraging communities to protect and take ownership of the infrastructure.
Electricity Expected to Strengthen Agricultural Processing
The projects are expected to support households, businesses and productive activities in the beneficiary areas, including communities known for groundnut, millet, sorghum and soybean production.
Access to electricity could enable local processors to use electric machinery to produce groundnut oil and kuli-kuli, potentially increasing processing capacity and improving the marketability of agricultural products.
The area also has traditional occupations, including blacksmithing, weaving and dyeing, which could benefit from more reliable electricity.
In addition to supporting economic activities, the mini-grid infrastructure is expected to provide power to a primary healthcare centre in the Gabazawa community, which the statement said had previously operated without electricity.
Reliable power at the facility could support healthcare services, although the extent of the improvement will depend on the consistency and affordability of electricity supply.
Alfuttaim Says Eight More Sites Are Under Development
Alfuttaim co-founder Dr. Nabilah Sani welcomed the completion of the projects, saying the installations would serve homes and support agricultural productivity.
She thanked the Federal Government for facilitating the funding support that helped bring the projects to completion.
Sani also disclosed that the two commissioned locations were part of 10 sites currently under development in Kano State, indicating that the company’s mini-grid investment programme extends beyond the latest installations.
She urged residents to protect the infrastructure and avoid vandalism to ensure the projects remain operational and continue delivering benefits.
The commissioning reflects ongoing efforts to expand Nigeria’s electricity network through off-grid solutions, particularly in communities where conventional grid supply remains unavailable or inadequate. Sustaining the benefits will depend on reliable operations, affordable tariffs and effective maintenance of the infrastructure.